All headspace gas samples will be run on GC3 (C1-C3). Gas void samples or samples containing higher hydrocarbons will be run on the NGA.

Titrations

The ph/alkalinity measures are routinely done (in real-time) by the Scientists with the Technician setting up the instruments. Chlorinity titrations are up to the Scientists as to if they want them done because chloride concentrations are measured on the IC.

IC

To determine anion and cation elemental concentrations. Wait until you have collected enough samples for a batch (ie. end of a hole). The Scientists can assist in preparing the samples but the Technician will set-up and run the instrument.

SPEC

Ammonium and phosphate are routinely measured. It's a good idea to wait until you have enough samples for an entire batch (ie. end of a hole), as it is a time-consuming process.

ICP 

The ICP-OES system will measure specific minor and major element concentrations of porewater, sediment (need approval) and hard rock. Wait until you have collected enough samples to run an entire batch (ie. end of a hole). Argon is limited, and the machine requires a significant amount of prep time. The Scientists can help prepare the samples but the Technician will set-up and run the instrument.

Coulometer

Crushing, weighing and running carbonate samples require a significant portion of time. During the initial discussion of the sampling protocol, the Scientists will decide on where they want to take the sample for the carbonate/EA analyses. It can be taken from the IW squeezecake or at the sample table after the core is split. Either way, these samples will have to be freeze-dried (typically for twelve hours) and then crushed/homogenized using a mortar and pestle. Usually the Scientists will prepare and run the analyses and the Technicians will set-up the system.

CHNS

Again, weighing and running the samples on this instrument is time-intensive and it be best to have a good sized batch ready before running. Usually the Scientists will weigh out the samples and the Technician will set-up the instrument and sequences. The combustion column needs to be replaced after approximately 100 samples.

SRA

The SRA is not routinely used but is part of our safety monitoring protocol. You must know how it operates and make sure that it is ready if needed.

...

VI. Port call – Off Going